{"id":5506,"date":"2020-06-17T16:06:20","date_gmt":"2020-06-17T16:06:20","guid":{"rendered":"https:\/\/blog.infraspeak.com\/?p=5506"},"modified":"2026-04-02T18:37:33","modified_gmt":"2026-04-02T18:37:33","slug":"cronograma-de-manutencao-preventiva","status":"publish","type":"post","link":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/","title":{"rendered":"Como tra\u00e7ar um cronograma de manuten\u00e7\u00e3o preventiva"},"content":{"rendered":"<div id=\"bsf_rt_marker\"><\/div><p><span style=\"font-weight: 400;\">Quando falamos em <\/span><a href=\"https:\/\/blog.infraspeak.com\/pt-br\/manutencao-preventiva\/\"><span style=\"font-weight: 400;\">manuten\u00e7\u00e3o preventiva<\/span><\/a><span style=\"font-weight: 400;\">, \u00e9 inevit\u00e1vel pensar em planejamento. Mas n\u00e3o adianta ter um bom plano de manuten\u00e7\u00e3o preventiva se n\u00e3o tiver um cronograma eficiente, porque, dessa forma, a possibilidade de falhar na execu\u00e7\u00e3o \u00e9 maior. Seria o mesmo que ter uma excelente receita para uma cerveja artesanal, preparar o seu pr\u00f3prio malte, mostrar aos amigos\u2026 e depois estragar tudo porque devia ter deixado a mistura fermentar mais um dia. Planejamento nenhum funciona sem um cronograma e \u00e9 isso que nos traz a este passo a passo para tra\u00e7ar um calend\u00e1rio de manuten\u00e7\u00e3o preventiva.\u00a0<\/span><\/p>\n<p>&nbsp;<\/p>\n<h2><span style=\"font-weight: 400;\">0. Plano vs. Cronograma de manuten\u00e7\u00e3o preventiva\u00a0<\/span><\/h2>\n<p><span style=\"font-weight: 400;\">O ponto de partida para tra\u00e7ar um cronograma de manuten\u00e7\u00e3o preventiva \u00e9 distinguir o cronograma do plano em si. O <\/span><a href=\"https:\/\/blog.infraspeak.com\/pt-br\/criar-plano-de-manutencao\/\"><span style=\"font-weight: 400;\">plano de manuten\u00e7\u00e3o preventiva<\/span><\/a><span style=\"font-weight: 400;\"> estabelece prioridades com base na import\u00e2ncia dos ativos na opera\u00e7\u00e3o e define todas as tarefas que devem ser executadas ao longo do ano. De certa forma, \u00e9 como dizer que as crian\u00e7as precisam aprender \u201cPortugu\u00eas e Matem\u00e1tica\u201d \u2013 ou seja, n\u00e3o passa de uma declara\u00e7\u00e3o de inten\u00e7\u00f5es. Para que se concretize, \u00e9 preciso fazer o hor\u00e1rio escolar e dividir o tempo entre as disciplinas.\u00a0<\/span><\/p>\n<p>Para empresas que gerenciam m\u00faltiplas instala\u00e7\u00f5es, a complexidade do cronograma aumenta exponencialmente. Imagine ter que coordenar a manuten\u00e7\u00e3o de v\u00e1rios edif\u00edcios, cada um com suas particularidades e necessidades espec\u00edficas. Um <a href=\"https:\/\/infraspeak.com\/pt-br\/solucoes\/software-cafm\">software CAFM<\/a> pode centralizar e coordenar todos os cronogramas de manuten\u00e7\u00e3o preventiva em uma \u00fanica plataforma, transformando o caos em organiza\u00e7\u00e3o.<\/p>\n<p>&nbsp;<\/p>\n<p><span style=\"font-weight: 400;\">Este \u201chor\u00e1rio\u201d \u00e9, como voc\u00ea j\u00e1 deve ter entendido, o cronograma de manuten\u00e7\u00e3o preventiva. A grande dificuldade \u00e9 calcular o tempo exato que deve ser atribu\u00eddo para cada tarefa e encaix\u00e1-las no calend\u00e1rio da empresa. Se estimar tempo a mais para uma determinada atividade, vai desperdi\u00e7ar tempo e dinheiro. J\u00e1 no caso contr\u00e1rio, se reservar pouco tempo, corre o risco de atrasar toda a opera\u00e7\u00e3o, comprometer o plano e ter t\u00e9cnicos insatisfeitos. E como por aqui queremos ser uma fonte de qualidade de vida para todas as equipes de manuten\u00e7\u00e3o, vamos ao passo 1.<\/span><\/p>\n<p>&nbsp;<\/p>\n<h2><span style=\"font-weight: 400;\">1. Determinar a produtividade da m\u00e3o de obra\u00a0<\/span><\/h2>\n<h2><\/h2>\n<p><span style=\"font-weight: 400;\">A primeira coisa que deve ter em mente ao tra\u00e7ar um cronograma de manuten\u00e7\u00e3o preventiva \u00e9 a produtividade da m\u00e3o de obra. Onde queremos chegar com isto? \u00c9 fora da realidade pensar que os t\u00e9cnicos est\u00e3o executando o trabalho de manuten\u00e7\u00e3o 100% do tempo. Na verdade, estima-se que apenas 25-35% das horas laborais se destinam ao trabalho efetivo. Sim, voc\u00ea leu direito: se este n\u00famero estiver acima dos 30%, j\u00e1 pode considerar a sua equipe bem mais produtiva que a m\u00e9dia.\u00a0<\/span><\/p>\n<p>&nbsp;<\/p>\n<p><span style=\"font-weight: 400;\">As outras horas &#8220;improdutivas&#8221; s\u00e3o usadas para procurar ferramentas, desloca\u00e7\u00f5es, esclarecer d\u00favidas, interrup\u00e7\u00f5es e pausas. Mesmo que algum deste tempo possa ser otimizado com um bom cronograma (por exemplo, evitando desloca\u00e7\u00f5es desnecess\u00e1rias), \u00e9 importante ter expectativas realistas. Se voc\u00ea trabalha com um <a href=\"https:\/\/infraspeak.com\/pt-br\/solucoes\/software-cmms\">software CMMS<\/a>, use os dados dispon\u00edveis para entender quantas horas foram realmente passadas em trabalho de manuten\u00e7\u00e3o no per\u00edodo. (<a href=\"https:\/\/blog.infraspeak.com\/pt-br\/como-escolher-o-melhor-cmms\/\">software de gest\u00e3o de manuten\u00e7\u00e3o<\/a>)<\/p>\n<p>&nbsp;<\/p>\n<h2><span style=\"font-weight: 400;\">2. Analisar a lista de tarefas\u00a0<\/span><\/h2>\n<p><span style=\"font-weight: 400;\">Antes de partir para um novo cronograma, \u00e9 preciso lidar com o \u201celefante na sala\u201d: o <\/span><i><span style=\"font-weight: 400;\">backlog <\/span><\/i><span style=\"font-weight: 400;\">de tarefas. Ou, em bom portugu\u00eas, a lista de tarefas que ficaram em aberto sem conclus\u00e3o no plano de manuten\u00e7\u00e3o anterior. \u00c9 recomend\u00e1vel terminar essas tarefas pendentes antes de avan\u00e7ar com toda a velocidade para um cronograma novo. Afinal, voc\u00ea pode at\u00e9 fugir\u2026 mas n\u00e3o pode se esconder dessas demandas.\u00a0<\/span><\/p>\n<p>&nbsp;<\/p>\n<h2><span style=\"font-weight: 400;\">3. Mergulhar no plano de manuten\u00e7\u00e3o preventiva\u00a0<\/span><\/h2>\n<p><span style=\"font-weight: 400;\">Agora que chegou at\u00e9 aqui, \u00e9 hora de trazer verdades: voc\u00ea n\u00e3o pode tra\u00e7ar um bom cronograma de manuten\u00e7\u00e3o preventiva sem mergulhar a fundo no plano de manuten\u00e7\u00e3o preventiva. \u00c9 preciso analisar todas as tarefas para calcular quantos funcion\u00e1rios ser\u00e3o necess\u00e1rios para cada atividade, quantas horas deve alocar (tendo em considera\u00e7\u00e3o a produtividade m\u00e9dia que j\u00e1 falamos no passo 1) e quais materiais e ferramentas vai precisar para cada tarefa. Um <a href=\"https:\/\/infraspeak.com\/pt-br\/plataforma\/software-gestao-de-ativos\">software gest\u00e3o de ativos<\/a> pode facilitar essa an\u00e1lise detalhada.<\/p>\n<p>Para um cronograma de manuten\u00e7\u00e3o preventiva eficiente, \u00e9 essencial ter controle total sobre materiais e pe\u00e7as de reposi\u00e7\u00e3o. Afinal, de que adianta ter o cronograma perfeito se na hora H faltam os recursos necess\u00e1rios? Um <a href=\"https:\/\/infraspeak.com\/pt-br\/solucoes\/software-gestao-estoque\">software gest\u00e3o de estoque<\/a> integrado pode garantir que todos os materiais e ferramentas estejam dispon\u00edveis no momento certo, evitando atrasos que comprometem todo o planejamento.<\/p>\n<p>&nbsp;<\/p>\n<p><span style=\"font-weight: 400;\">H\u00e1 ainda outro ponto importante: o cronograma tamb\u00e9m deve considerar o melhor momento para fazer manuten\u00e7\u00e3o programada. Por exemplo, se estamos falando de um edif\u00edcio que precisa de uma cobertura nova, talvez seja mais prudente agendar estas obras para a \u00e9poca de f\u00e9rias, onde o pr\u00e9dio poder\u00e1 estar mais vazio. Se a situa\u00e7\u00e3o \u00e9 a renova\u00e7\u00e3o completa do sistema de refrigera\u00e7\u00e3o de um hotel, talvez seja melhor esperar pela baixa temporada. Um <a href=\"https:\/\/infraspeak.com\/pt-br\/solucoes\/software-gestao-facilities\">software gest\u00e3o de facilities<\/a> pode ajudar a coordenar esses cronogramas complexos. Fa\u00e7a um esfor\u00e7o para que o tempo de paradas planejado prejudique o menos poss\u00edvel os seus clientes.<\/p>\n<p>&nbsp;<\/p>\n<h2><span style=\"font-weight: 400;\">4. Definir prioridades\u00a0<\/span><\/h2>\n<p><span style=\"font-weight: 400;\">\u201cMas isso n\u00e3o devia estar definido no plano de manuten\u00e7\u00e3o?\u201d Claro que sim. Mas nenhum plano de manuten\u00e7\u00e3o, por melhor que seja, \u00e9 100% livre de erros. Por mais inconveniente que seja para todos os gestores de manuten\u00e7\u00e3o, o mundo n\u00e3o funciona como um algoritmo: os danos e os imprevistos v\u00e3o sempre acontecer. Uma forma de responder ao problema \u00e9 ter alguma flexibilidade em rela\u00e7\u00e3o ao cronograma di\u00e1rio e ser mais espec\u00edfico apenas nos planos mensais ou semanais.\u00a0\u00a0<\/span><\/p>\n<p>Al\u00e9m dos imprevistos operacionais, h\u00e1 outro fator que pode bagun\u00e7ar qualquer cronograma: as exig\u00eancias regulat\u00f3rias. Manter a conformidade \u00e9 fundamental em qualquer cronograma de manuten\u00e7\u00e3o preventiva, especialmente quando falamos de equipamentos cr\u00edticos ou ambientes regulamentados. Um <a href=\"https:\/\/infraspeak.com\/pt-br\/plataforma\/conformidade\">software de compliance<\/a> pode garantir que todas as atividades atendam aos requisitos legais e normativos, evitando surpresas desagrad\u00e1veis durante auditorias.<\/p>\n<p>&nbsp;<\/p>\n<p><span style=\"font-weight: 400;\">A outra dica \u00e9 definir prioridades claras sobre como alterar o cronograma durante um imprevisto. Como responder a cada tipo de risco? O que exige uma resposta imediata, mesmo que isso implique na parada do planejamento habitual? Quais s\u00e3o os tempos m\u00e1ximos de resposta que devem ser assegurados? \u201cPrever imprevistos\u201d \u00e9 um jogo que, por defini\u00e7\u00e3o, nunca podemos ganhar \u2013 mas podemos perder por menos. Assim, voc\u00ea consegue evitar os problemas com a lista de tarefas, como o que falamos no passo 2.<\/span><\/p>\n<p>&nbsp;<\/p>\n<h2><span style=\"font-weight: 400;\">5. Agendar o dia a dia<\/span><\/h2>\n<p><span style=\"font-weight: 400;\">Chegamos ao \u00faltimo passo. Ent\u00e3o, aqui, vale a pena recapitular todos os pontos. Voc\u00ea j\u00e1 sabe quantas horas s\u00e3o necess\u00e1rias para cada tarefa (realisticamente, tendo em conta a produtividade real!); quais tarefas devem ser finalizadas; quais tem para come\u00e7ar e quais recursos ser\u00e3o necess\u00e1rios para cada uma delas. Ent\u00e3o, agora s\u00f3 falta juntar as pe\u00e7as que estavam no meio do quebra-cabe\u00e7a e foram deixadas para o final: as datas e as horas.\u00a0<\/span><\/p>\n<p>Quando as equipes de manuten\u00e7\u00e3o trabalham em campo, a coordena\u00e7\u00e3o se torna ainda mais desafiadora. Como garantir que os t\u00e9cnicos sigam o cronograma quando est\u00e3o espalhados por diferentes locais? Um <a href=\"https:\/\/infraspeak.com\/pt-br\/solucoes\/software-field-service-management\">software field service management<\/a> pode otimizar significativamente a execu\u00e7\u00e3o do cronograma de manuten\u00e7\u00e3o preventiva, permitindo acompanhamento em tempo real e ajustes quando necess\u00e1rio.<\/p>\n<p>&nbsp;<\/p>\n<p><span style=\"font-weight: 400;\">Finalmente, e para completar o ciclo, lembre-se que um cronograma de manuten\u00e7\u00e3o preventiva bem delineado tamb\u00e9m permite aumentar a produtividade. Evite agendar tarefas seguidas que obriguem que seus t\u00e9cnicos fa\u00e7am grandes desloca\u00e7\u00f5es, junte atividades que precisam do mesmo tipo de ferramentas e tente incluir todas as informa\u00e7\u00f5es necess\u00e1rias nas ordens de servi\u00e7o para que eles possam agir mais r\u00e1pido.<\/span><\/p>\n<p><span style=\"font-weight: 400;\">___<\/span><\/p>\n<p><span style=\"font-weight: 400;\">Quer saber como o Infraspeak pode te ajudar a construir planos e cronogramas de manuten\u00e7\u00e3o preventiva? <\/span><a href=\"https:\/\/infraspeak.com\/pt-br\/demo\/\"><span style=\"font-weight: 400;\">Fale com um dos nossos especialistas<\/span><\/a><span style=\"font-weight: 400;\">.<\/span><\/p>\n<p><a href=\"https:\/\/infraspeak.com\/demo\/?utm_medium=blog&amp;utm_source=blog&amp;utm_campaign=cronograma-mp&amp;utm_content=blogpost\"><img fetchpriority=\"high\" decoding=\"async\" class=\"alignnone size-full wp-image-3725\" src=\"http:\/\/blog.infraspeak.com\/wp-content\/uploads\/2019\/11\/PT-Demo-Banner.png\" alt=\"\" width=\"1694\" height=\"582\" srcset=\"https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2019\/11\/PT-Demo-Banner.png 1694w, https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2019\/11\/PT-Demo-Banner-300x103.png 300w, https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2019\/11\/PT-Demo-Banner-768x264.png 768w, https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2019\/11\/PT-Demo-Banner-1024x352.png 1024w\" sizes=\"(max-width: 1694px) 100vw, 1694px\" \/><\/a><\/p>\n","protected":false},"excerpt":{"rendered":"<p>N\u00e3o adianta ter um bom plano de manuten\u00e7\u00e3o preventiva se n\u00e3o tiver um bom cronograma para o executar. Saiba como o fazer, passo a passo.<\/p>\n","protected":false},"author":54,"featured_media":4400,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"content-type":"","footnotes":"","_wp_rev_ctl_limit":""},"categories":[366],"tags":[551,641],"class_list":["post-5506","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-manutencao","tag-cronograma","tag-manutencao-preventiva-pt-br"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v27.3 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Crie um cronograma de manuten\u00e7\u00e3o preventiva &#8226; Infraspeak Blog<\/title>\n<meta name=\"description\" content=\"N\u00e3o adianta ter um bom plano de manuten\u00e7\u00e3o preventiva se n\u00e3o tiver um bom cronograma para o executar. Saiba como o fazer, passo a passo.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/\" \/>\n<meta property=\"og:locale\" content=\"pt_BR\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Crie um cronograma de manuten\u00e7\u00e3o preventiva &#8226; Infraspeak Blog\" \/>\n<meta property=\"og:description\" content=\"N\u00e3o adianta ter um bom plano de manuten\u00e7\u00e3o preventiva se n\u00e3o tiver um bom cronograma para o executar. Saiba como o fazer, passo a passo.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/\" \/>\n<meta property=\"og:site_name\" content=\"Infraspeak Blog\" \/>\n<meta property=\"article:publisher\" content=\"https:\/\/www.facebook.com\/infraspeakmaintenance\" \/>\n<meta property=\"article:published_time\" content=\"2020-06-17T16:06:20+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2026-04-02T18:37:33+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2020\/03\/AdobeStock_302181481-min.jpeg\" \/>\n\t<meta property=\"og:image:width\" content=\"6720\" \/>\n\t<meta property=\"og:image:height\" content=\"4480\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/jpeg\" \/>\n<meta name=\"author\" content=\"Infraspeak Team\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:creator\" content=\"@infraspeak\" \/>\n<meta name=\"twitter:site\" content=\"@infraspeak\" \/>\n<meta name=\"twitter:label1\" content=\"Escrito por\" \/>\n\t<meta name=\"twitter:data1\" content=\"Infraspeak Team\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. tempo de leitura\" \/>\n\t<meta name=\"twitter:data2\" content=\"7 minutos\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-br\\\/cronograma-de-manutencao-preventiva\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-br\\\/cronograma-de-manutencao-preventiva\\\/\"},\"author\":{\"name\":\"Infraspeak Team\",\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-pt\\\/#\\\/schema\\\/person\\\/b53887f01881a658b4cc1bf25f2d4377\"},\"headline\":\"Como tra\u00e7ar um cronograma de manuten\u00e7\u00e3o preventiva\",\"datePublished\":\"2020-06-17T16:06:20+00:00\",\"dateModified\":\"2026-04-02T18:37:33+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-br\\\/cronograma-de-manutencao-preventiva\\\/\"},\"wordCount\":1368,\"publisher\":{\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-pt\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-br\\\/cronograma-de-manutencao-preventiva\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/blog.infraspeak.com\\\/wp-content\\\/uploads\\\/2020\\\/03\\\/AdobeStock_302181481-min.jpeg\",\"keywords\":[\"cronograma\",\"manuten\u00e7\u00e3o preventiva\"],\"articleSection\":[\"Manuten\u00e7\u00e3o\"],\"inLanguage\":\"pt-BR\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-br\\\/cronograma-de-manutencao-preventiva\\\/\",\"url\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-br\\\/cronograma-de-manutencao-preventiva\\\/\",\"name\":\"Crie um cronograma de manuten\u00e7\u00e3o preventiva &#8226; Infraspeak Blog\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-pt\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-br\\\/cronograma-de-manutencao-preventiva\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-br\\\/cronograma-de-manutencao-preventiva\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/blog.infraspeak.com\\\/wp-content\\\/uploads\\\/2020\\\/03\\\/AdobeStock_302181481-min.jpeg\",\"datePublished\":\"2020-06-17T16:06:20+00:00\",\"dateModified\":\"2026-04-02T18:37:33+00:00\",\"description\":\"N\u00e3o adianta ter um bom plano de manuten\u00e7\u00e3o preventiva se n\u00e3o tiver um bom cronograma para o executar. Saiba como o fazer, passo a passo.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-br\\\/cronograma-de-manutencao-preventiva\\\/#breadcrumb\"},\"inLanguage\":\"pt-BR\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/blog.infraspeak.com\\\/pt-br\\\/cronograma-de-manutencao-preventiva\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"pt-BR\",\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-br\\\/cronograma-de-manutencao-preventiva\\\/#primaryimage\",\"url\":\"https:\\\/\\\/blog.infraspeak.com\\\/wp-content\\\/uploads\\\/2020\\\/03\\\/AdobeStock_302181481-min.jpeg\",\"contentUrl\":\"https:\\\/\\\/blog.infraspeak.com\\\/wp-content\\\/uploads\\\/2020\\\/03\\\/AdobeStock_302181481-min.jpeg\",\"width\":6720,\"height\":4480,\"caption\":\"Plano de manuten\u00e7\u00e3o preventiva | Plan de mantenimiento preventivo | Preventive maintenance plan | planned preventive maintenance\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-br\\\/cronograma-de-manutencao-preventiva\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/blog.infraspeak.com\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Como tra\u00e7ar um cronograma de manuten\u00e7\u00e3o preventiva\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-pt\\\/#website\",\"url\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-pt\\\/\",\"name\":\"Infraspeak Blog\",\"description\":\"All About Maintenance and Facilities Management\",\"publisher\":{\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-pt\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-pt\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"pt-BR\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-pt\\\/#organization\",\"name\":\"Infraspeak\",\"url\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-pt\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"pt-BR\",\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-pt\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/blog.infraspeak.com\\\/wp-content\\\/uploads\\\/2018\\\/11\\\/is-logo@2x.png\",\"contentUrl\":\"https:\\\/\\\/blog.infraspeak.com\\\/wp-content\\\/uploads\\\/2018\\\/11\\\/is-logo@2x.png\",\"width\":544,\"height\":180,\"caption\":\"Infraspeak\"},\"image\":{\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-pt\\\/#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/www.facebook.com\\\/infraspeakmaintenance\",\"https:\\\/\\\/x.com\\\/infraspeak\",\"https:\\\/\\\/www.instagram.com\\\/infraspeak\\\/\",\"http:\\\/\\\/www.linkedin.com\\\/company\\\/infraspeak\",\"https:\\\/\\\/www.youtube.com\\\/channel\\\/UCOdjKyhSD9RJbRhuP-S8Avw\"]},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-pt\\\/#\\\/schema\\\/person\\\/b53887f01881a658b4cc1bf25f2d4377\",\"name\":\"Infraspeak Team\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"pt-BR\",\"@id\":\"https:\\\/\\\/blog.infraspeak.com\\\/wp-content\\\/uploads\\\/2023\\\/02\\\/296167549_2627985274000609_8314221938057526692_n-120x120.jpg\",\"url\":\"https:\\\/\\\/blog.infraspeak.com\\\/wp-content\\\/uploads\\\/2023\\\/02\\\/296167549_2627985274000609_8314221938057526692_n-120x120.jpg\",\"contentUrl\":\"https:\\\/\\\/blog.infraspeak.com\\\/wp-content\\\/uploads\\\/2023\\\/02\\\/296167549_2627985274000609_8314221938057526692_n-120x120.jpg\",\"caption\":\"Infraspeak Team\"},\"url\":\"https:\\\/\\\/blog.infraspeak.com\\\/pt-br\\\/author\\\/infraspeakteam\\\/\"}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Crie um cronograma de manuten\u00e7\u00e3o preventiva &#8226; Infraspeak Blog","description":"N\u00e3o adianta ter um bom plano de manuten\u00e7\u00e3o preventiva se n\u00e3o tiver um bom cronograma para o executar. Saiba como o fazer, passo a passo.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/","og_locale":"pt_BR","og_type":"article","og_title":"Crie um cronograma de manuten\u00e7\u00e3o preventiva &#8226; Infraspeak Blog","og_description":"N\u00e3o adianta ter um bom plano de manuten\u00e7\u00e3o preventiva se n\u00e3o tiver um bom cronograma para o executar. Saiba como o fazer, passo a passo.","og_url":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/","og_site_name":"Infraspeak Blog","article_publisher":"https:\/\/www.facebook.com\/infraspeakmaintenance","article_published_time":"2020-06-17T16:06:20+00:00","article_modified_time":"2026-04-02T18:37:33+00:00","og_image":[{"width":6720,"height":4480,"url":"https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2020\/03\/AdobeStock_302181481-min.jpeg","type":"image\/jpeg"}],"author":"Infraspeak Team","twitter_card":"summary_large_image","twitter_creator":"@infraspeak","twitter_site":"@infraspeak","twitter_misc":{"Escrito por":"Infraspeak Team","Est. tempo de leitura":"7 minutos"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/#article","isPartOf":{"@id":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/"},"author":{"name":"Infraspeak Team","@id":"https:\/\/blog.infraspeak.com\/pt-pt\/#\/schema\/person\/b53887f01881a658b4cc1bf25f2d4377"},"headline":"Como tra\u00e7ar um cronograma de manuten\u00e7\u00e3o preventiva","datePublished":"2020-06-17T16:06:20+00:00","dateModified":"2026-04-02T18:37:33+00:00","mainEntityOfPage":{"@id":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/"},"wordCount":1368,"publisher":{"@id":"https:\/\/blog.infraspeak.com\/pt-pt\/#organization"},"image":{"@id":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/#primaryimage"},"thumbnailUrl":"https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2020\/03\/AdobeStock_302181481-min.jpeg","keywords":["cronograma","manuten\u00e7\u00e3o preventiva"],"articleSection":["Manuten\u00e7\u00e3o"],"inLanguage":"pt-BR"},{"@type":"WebPage","@id":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/","url":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/","name":"Crie um cronograma de manuten\u00e7\u00e3o preventiva &#8226; Infraspeak Blog","isPartOf":{"@id":"https:\/\/blog.infraspeak.com\/pt-pt\/#website"},"primaryImageOfPage":{"@id":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/#primaryimage"},"image":{"@id":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/#primaryimage"},"thumbnailUrl":"https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2020\/03\/AdobeStock_302181481-min.jpeg","datePublished":"2020-06-17T16:06:20+00:00","dateModified":"2026-04-02T18:37:33+00:00","description":"N\u00e3o adianta ter um bom plano de manuten\u00e7\u00e3o preventiva se n\u00e3o tiver um bom cronograma para o executar. Saiba como o fazer, passo a passo.","breadcrumb":{"@id":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/#breadcrumb"},"inLanguage":"pt-BR","potentialAction":[{"@type":"ReadAction","target":["https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/"]}]},{"@type":"ImageObject","inLanguage":"pt-BR","@id":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/#primaryimage","url":"https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2020\/03\/AdobeStock_302181481-min.jpeg","contentUrl":"https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2020\/03\/AdobeStock_302181481-min.jpeg","width":6720,"height":4480,"caption":"Plano de manuten\u00e7\u00e3o preventiva | Plan de mantenimiento preventivo | Preventive maintenance plan | planned preventive maintenance"},{"@type":"BreadcrumbList","@id":"https:\/\/blog.infraspeak.com\/pt-br\/cronograma-de-manutencao-preventiva\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/blog.infraspeak.com\/"},{"@type":"ListItem","position":2,"name":"Como tra\u00e7ar um cronograma de manuten\u00e7\u00e3o preventiva"}]},{"@type":"WebSite","@id":"https:\/\/blog.infraspeak.com\/pt-pt\/#website","url":"https:\/\/blog.infraspeak.com\/pt-pt\/","name":"Infraspeak Blog","description":"All About Maintenance and Facilities Management","publisher":{"@id":"https:\/\/blog.infraspeak.com\/pt-pt\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/blog.infraspeak.com\/pt-pt\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"pt-BR"},{"@type":"Organization","@id":"https:\/\/blog.infraspeak.com\/pt-pt\/#organization","name":"Infraspeak","url":"https:\/\/blog.infraspeak.com\/pt-pt\/","logo":{"@type":"ImageObject","inLanguage":"pt-BR","@id":"https:\/\/blog.infraspeak.com\/pt-pt\/#\/schema\/logo\/image\/","url":"https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2018\/11\/is-logo@2x.png","contentUrl":"https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2018\/11\/is-logo@2x.png","width":544,"height":180,"caption":"Infraspeak"},"image":{"@id":"https:\/\/blog.infraspeak.com\/pt-pt\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/www.facebook.com\/infraspeakmaintenance","https:\/\/x.com\/infraspeak","https:\/\/www.instagram.com\/infraspeak\/","http:\/\/www.linkedin.com\/company\/infraspeak","https:\/\/www.youtube.com\/channel\/UCOdjKyhSD9RJbRhuP-S8Avw"]},{"@type":"Person","@id":"https:\/\/blog.infraspeak.com\/pt-pt\/#\/schema\/person\/b53887f01881a658b4cc1bf25f2d4377","name":"Infraspeak Team","image":{"@type":"ImageObject","inLanguage":"pt-BR","@id":"https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2023\/02\/296167549_2627985274000609_8314221938057526692_n-120x120.jpg","url":"https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2023\/02\/296167549_2627985274000609_8314221938057526692_n-120x120.jpg","contentUrl":"https:\/\/blog.infraspeak.com\/wp-content\/uploads\/2023\/02\/296167549_2627985274000609_8314221938057526692_n-120x120.jpg","caption":"Infraspeak Team"},"url":"https:\/\/blog.infraspeak.com\/pt-br\/author\/infraspeakteam\/"}]}},"_links":{"self":[{"href":"https:\/\/blog.infraspeak.com\/pt-br\/wp-json\/wp\/v2\/posts\/5506","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/blog.infraspeak.com\/pt-br\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/blog.infraspeak.com\/pt-br\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/blog.infraspeak.com\/pt-br\/wp-json\/wp\/v2\/users\/54"}],"replies":[{"embeddable":true,"href":"https:\/\/blog.infraspeak.com\/pt-br\/wp-json\/wp\/v2\/comments?post=5506"}],"version-history":[{"count":5,"href":"https:\/\/blog.infraspeak.com\/pt-br\/wp-json\/wp\/v2\/posts\/5506\/revisions"}],"predecessor-version":[{"id":34856,"href":"https:\/\/blog.infraspeak.com\/pt-br\/wp-json\/wp\/v2\/posts\/5506\/revisions\/34856"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/blog.infraspeak.com\/pt-br\/wp-json\/wp\/v2\/media\/4400"}],"wp:attachment":[{"href":"https:\/\/blog.infraspeak.com\/pt-br\/wp-json\/wp\/v2\/media?parent=5506"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/blog.infraspeak.com\/pt-br\/wp-json\/wp\/v2\/categories?post=5506"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/blog.infraspeak.com\/pt-br\/wp-json\/wp\/v2\/tags?post=5506"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}